News
MMPI Names Falanga President
MMPI announced that Mark Falanga, a 17-year veteran of the organization and accomplished industry leader, has been named president effective July 23. Falanga succeeds Christopher Kennedy, who has served as president since 2000 and recently announced his departure from the organization to focus on civic and philanthropic endeavors.
… Read More
|
June 23, 2011 |
Construction Update - 6/23/11
On Mall B, the eighth Caisson was poured earlier this week, a deep foundation support that is constructed by placing fresh concrete and reinforcing steel into a drilled shaft. These reinforced concrete piles are cast in holes of predetermined diameters and depths drilled through soil to reach bedrock.
Foundation work on the Concourse level of the future Convention Center continues with formwork for pilasters scheduled to begin shortly. A pilaster is a rectangular support that resembles a flat column.
… Read More
|
June 23, 2011 |
Construction Update - 6/16/11
North of Lakeside Avenue, the North Bridge demolition continued on Mall C and is now 95% complete. Debris removal will continue. Interior demolition is 85% complete in existing Exhibit Halls ‘’C’’ and ‘’D’’ on the lower level. Underneath Lakeside Avenue, temporary steel support of the roadway continues with targeted column demolition scheduled for next week. Mall C demolition continued with additional roof removal continuing this week. Micro-pile work continues in the Ballroom area.
… Read More
|
June 16, 2011 |
Construction Update - 6/9/11
Crews have begun installing caissons, driving down the large, four-foot diameter structures more than 150 feet until they can be locked into the bedrock. The second caisson was completed earlier this week. Pre-cores for caissons continue with 60 of the 66 completed and more than 100 of the 240+ micropiles have also been completed.
… Read More
|
June 9, 2011 |
Regions hope industry clusters will draw jobs
FROM USA TODAY: Alex Nudelman, a strapping 49-year-old, confidently pushes buttons on a computer-controlled milling machine and suggests it's ready to sculpt a small piece of metal. His instructor stops him, noting Nudelman has not programmed in all the tools needed to shape the metal block.
A journeyman autoworker who was laid off in 2009, Nudelman is taking a community college class here so he can work on the more sophisticated gear powering the region's growing cluster of medical device makers. If all goes well, he may soon be churning out spinal implants instead of seat brackets.
"I'm trying to compare the new technology with my old experience, and sometimes it's helpful, and sometimes" it isn't, Nudelman says. But, the Russia native adds, blue eyes brightening, "It's the future."
… Read More
|
June 7, 2011 |
Construction Update - 6/2/11
Mall C demolition is roughly 95% complete with the foundations for the East Stair Tower currently being removed. Interior demolition has passed the halfway mark on the existing Exhibit Halls ''C'' and ''D'' on the lower level of Mall C. On the former Mall B, crews have completed more than 50 pre-cores for caissons with caisson drilling beginning earlier this week.
… Read More
|
June 2, 2011 |
Construction Update - 5/26/11
Mall C demolition is roughly 95% complete with the foundations for the East Stair Tower to be removed by early next week. Interior demolition is 50% completed on the existing Exhibit Halls ‘’C’’ and ‘’D’’ on the lower level of Mall C. On the former Mall B, crews have completed more than 50 pre-cores for caissons with caisson drilling underway. More than 60 micro-piles are complete. Demolition continued on Mall B next to Public Auditorium. Metal sheeting continued along St. Clair Avenue, moving westward, with this activity expected to be completed by next week. With the sheeting work complete, crews will now begin excavation down to finish exhibit hall floor. Continued demolition of the topping slab and 4’ interstitial sand volume, this work is approximately 95% complete. The temporary construction ramp being constructed will extend from the Exhibit hall floor to Lakeside Avenue.
… Read More
|
May 26, 2011 |
q & a: tony prusak, director of convention sales for medical mart & convention center
FROM FRESH WATER: As Downtown bustles with construction at the site of the future Medical Mart and Convention Center (MMCC), a different sort of energy bubbles a few blocks away at the offices of Merchandise Mart Properties Inc. (MMPI). The private management organization is tasked with filling the Medical Mart with tenants and booking events for the new Convention Center well in advance of its 2013 completion.
… Read More
|
May 26, 2011 |
Construction Update - 5/19/11
On Wednesday, May 18, MMPI, along with Turner Construction Company, Minority Business Solutions, and North Coast Minority Media hosted an SBE Bid Package Event at Public Auditorium to coincide with the release of BP-22 (Painting and Wallcovering), BP-23 (Carpet), BP-24 (Ceramic & Quarry Tile), BP-25 (Terrazzo), BP-26 (Interior Glass), BP-27 (Ornamental Iron & Railings), BP-28 (Carpentry, including rough, finish, millwork, install doors/frames/hardware, toilet partitions, toilet accessories, lockers), and BP-47 (Site Work, including site earthwork, site concrete, site utilities, asphalt, and landscaping).
… Read More
|
May 19, 2011 |
Construction Update - 5/12/11
The demolition and haul out of materials and debris from the five buildings on the future Medical Mart site has been completed. The 113 Building was demolished in April, the last structure to be demolished at the corner of St. Clair and Ontario. In three months, crews demolished the Justice Center parking deck, the Chicago Title and County Annex buildings, the Sportsmans Restaurant, and the 113 Building. Soldier pile installation has been completed around the former 113 Building while backfilling, lagging and tie-backs continue.
… Read More
|
May 12, 2011 |

